Multilayer PCB Quick Turn

A quick-turn multilayer board is limited by lamination cycles and drilling, not by how early the order arrives. Knowing the bottle necks makes the promise realistic.

Hitech Circuits Engineering Desk

Shenzhen, China · PCB fabrication and assembly

2 min read

Published:

Last updated:

Technical review: Process figures checked against our published capability sheet. View capability sheet

Multilayer PCB Quick Turn

Where the time goes

A multilayer board passes through inner-layer imaging and etching, lamination, drilling, plating, outer-layer imaging, solder mask, finish and test. Lamination and drilling dominate; every extra lamination cycle adds a full day or more.

What fits a three-day window

  • Four to six layers, one lamination cycle.
  • Standard FR-4, 1 oz outer copper, HASL or lead-free HASL.
  • Minimum trace 0.075 mm and no laser vias.
  • Electrical test plus visual inspection.

What moves the board out of it

Eight layers and above, sequential lamination for HDI, heavy copper beyond the standard range, impedance coupons with a tight tolerance, and ceramic or high-frequency substrates all add steps. They are still buildable quickly, but the quotation should carry a realistic date rather than a generic "24 hours".

Our standard windows are 1–3 days for prototypes and 4–10 days for mid-volume, with 1–38 layers and boards up to 580 × 1900 mm. If the schedule is tight, send the stackup with the enquiry — the date depends on the build, not only on quantity.

Technical Specifications

Prototype lead time
1–3 days
Mid-volume lead time
4–10 days
Layer count
1–38 layers
Maximum board size
580 × 1900 mm

Frequently Asked Questions

  • What decides whether a multilayer board can be built in three days?

    The number of lamination cycles, the drill programme and the finish. A four- or six-layer board with one lamination and HASL fits a three-day window; eight layers and above, sequential lamination, impedance coupons or a specialised finish add process steps that cannot be compressed.

  • Does quick turn change the quality checks?

    No. The same electrical test, AOI and final inspection apply; what changes is queue priority. If the design includes impedance control, the coupons are built with the panel and measured, which is why that requirement should be stated when the order is placed.